Figure 1. Current critical power (kilowatts (kW))
| Usage | Capacity | |
|---|---|---|
| Baseline | 270 | 360 |
| 2011 | 290 | 360 |
| 2012 | 330 | 360 |
Figure 2. Martin renovation estimated spending
Millions of dollars ($280.4 million estimated budget)
| Budget | Actual | |
|---|---|---|
| Design | 15.4 | 4.3 |
| Construction | 188.3 | 0 |
| Leased Space | 76.7 | 0.1 |
| Total | 280.4 | 4.4 |
Figure 3. Board's 2012 and 2013 budgets: forecast vs. actual
Millions of dollars
| Forecast | Actual | |
|---|---|---|
| 2012 | $14.40 | $497.40 |
| 2013 | $560.00 | 0 |